Deposit and Holdback Clauses in Construction Loans: A Practical Guide

Construction financing is inherently riskier than a standard mortgage. Deposit and holdback clauses (also called retainage or escrow holdbacks) are common tools lenders and borrowers use to reduce that risk, ensure work is completed, and keep funds flowing in a controlled way.

In my 15 years originating and servicing construction loans, I’ve seen well-structured clauses prevent delays, reduce lien claims, and keep projects within budget. Below is a practical, step-by-step look at why these clauses exist, how they operate, and how to negotiate and manage them.


Why do lenders and borrowers use deposit and holdback clauses?

  • Protect the lender’s capital by preventing the borrower or contractor from receiving full funds before performance is verified.
  • Give the borrower leverage to ensure contractors finish work and correct defects before final payment.
  • Encourage timely completion by tying permanent release of funds to inspections, certificates of occupancy, or lien waivers.

Authoritative guidance on mortgage protections and escrow practices can be found at the Consumer Financial Protection Bureau (https://www.consumerfinance.gov/) and the U.S. Small Business Administration (https://www.sba.gov/).


Common types of clauses and how they differ

  • Deposit clause (upfront payment): requires the borrower to contribute cash, equity, or a letter of credit at closing or prior to the first draw. Typical ranges:

  • Residential/low-risk: commonly 5–10% of total project cost.

  • Commercial or higher-risk projects: often 10–20% (or higher) depending on borrower credit, contractor experience and market conditions.

  • Holdback / retainage (withheld funds): a percentage of each draw or of the total loan held until conditions are met. Two common forms:

  • Percentage retainage: lender withholds a fixed percent (e.g., 5–10%) of each draw and releases the accumulated retainage at project completion and final lien releases.

  • Milestone/escrow holdback: a lump amount withheld and placed in escrow until a specific milestone (final inspection, occupancy certificate) is satisfied.

  • Conditional release / lien waiver schemes: the lender may require contractors and subcontractors to provide conditional lien waivers tied to each draw to reduce mechanics’ lien exposure.

For more on the inspection-and-draw process, see our guide to construction draws and inspections (construction draws and inspections).


How the typical holdback process works (step-by-step)

  1. Loan documentation defines the deposit, holdback percentage, milestone schedule, and release conditions.
  2. Borrower pays the deposit (or posts equivalent collateral) at or before closing.
  3. Lender authorizes draws per a schedule after verifying invoices, lien waivers, and required inspections.
  4. Lender withholds the agreed retainage amount from each draw or keeps a lump sum in escrow.
  5. As milestones are verified (third-party inspections, county permits, certificate of occupancy), the lender releases portions or all of the holdback.
  6. Final releases usually require final lien waivers from the contractor and major vendors, final inspection, and any required title or legal clearances.

This timeline is closely tied to the draw schedule. See our article on managing draw schedules for best practices (draw schedules).


Example (simple math)

Project budget: $1,000,000
Deposit required: 10% = $100,000 (paid by borrower at closing)
Lender issues draws totaling $900,000 across stages. Lender withholds 10% retainage on each draw = $90,000 held.

The contractor receives the $900,000 in staged payments (less retainage). Once the work is complete and final inspections/lien waivers are in, the lender releases the $90,000 retainage (or applies it to cure outstanding liens/deficiencies).

Note: A lender might instead require a $90,000 escrow holdback that is explicitly accounted for on the loan closing statement.


Key documentation and controls lenders typically require

  • Construction contract and cost breakdown form.
  • Detailed draw schedule tied to measurable milestones.
  • Third-party inspections or architect’s certificates for each draw.
  • Conditional lien waivers or unconditional waivers on release.
  • Escrow account agreements and release triggers.
  • Performance and payment bonds (for larger projects).

These controls help reduce the risk of mechanics’ liens and fund misuse. State lien laws vary widely, so counsel should confirm local requirements.


Negotiation points borrowers should prioritize

  • Reasonable deposit size and timing: push for lower, staged deposits where possible.
  • Define clear, objective holdback release conditions (inspections, CO, certificate from architect).
  • Limit the lender’s discretionary release powers; require written notices and cure periods before withholding additional funds.
  • Allow for partial releases tied to independent inspections so the borrower doesn’t have to wait for one final release.
  • Require use of standard conditional lien waivers tied to payment periods to protect against contractor claims.

In my experience, borrowers who prepare detailed schedules and provide strong contractor references can often reduce retainage percentages or accelerate release conditions.


Operational risks and common mistakes

  • Poor documentation: not attaching required lien waivers or inspection reports delays releases.
  • Confusing escrow parties: ensure the escrow agent or title company has written instructions from the lender and borrower.
  • Undervaluing contingency: holdbacks reduce available cash for unforeseen costs; borrowers should plan contingency funds outside the holdback.
  • Failing to manage subcontractor claims: if subcontractors aren’t paid or don’t sign waivers, they can file mechanics’ liens that complicate final releases.

Always require lien-waiver forms to be completed correctly and retained with each draw file.


Disputes, remedies, and alternatives

  • Independent inspection and dispute resolution language in the loan documents speeds resolution.
  • Performance bonds or payment bonds can substitute for retainage on certain projects and give subcontractors direct protection (useful for large commercial builds).
  • Holdback escrow can be administered by a neutral third party (title company) to avoid lender/borrower conflicts.

When disputes escalate, common legal remedies include stop notices, mechanic’s lien enforcement, or invoking performance bonds. Consult construction counsel quickly if a lien notice appears.


Tax and accounting considerations (high-level)

  • For a borrower (owner/developer), deposit and holdback funds are part of project financing. Capitalized costs generally include amounts paid for construction; consult a tax advisor for specific treatment.
  • For contractors, retainage is typically treated as a receivable until collected. State and federal rules for revenue recognition and estimated taxes can apply—contractors should coordinate with their accountant.

This is general information only; talk to a CPA about timing of income recognition and deductions.


Practical checklist for borrowers and lenders

For borrowers:

  • Negotiate deposit and retainage percentages before signing.
  • Confirm draw schedule and inspection protocols in writing.
  • Maintain a project file with lien waivers, permits, and inspection reports.
  • Keep contingency reserves outside the loaned funds.

For lenders:

  • Require clear milestone definitions and independent inspections.
  • Use conditional/unconditional waivers consistently.
  • Consider escrow administration for contentious projects.
  • Review contractor references and performance bonds for large projects.

Where to learn more

  • Construction holdback funds (FinHelp) — see our deep dive on construction holdbacks (construction holdback funds).
  • Construction draws, inspections, and interest handling (FinHelp) — procedural guidance for staged draws (construction draws and inspections).
  • Managing construction draw schedules (FinHelp) — practical tips to align disbursements with project risk (draw schedules).

Authoritative resources: Consumer Financial Protection Bureau (https://www.consumerfinance.gov/) and U.S. Small Business Administration guidance on construction and contracting (https://www.sba.gov/). State bar associations and local building departments publish mechanics’ lien rules — check those resources for local law.


Professional disclaimer

This article is educational and reflects general industry practice and my professional experience in construction lending. It does not constitute legal, tax, or financial advice. For advice tailored to your project, consult a licensed attorney, a tax professional, or a construction lender.